Any newly-built, expanded or rebuilt basic construction project (engineering) and technological transformation project shall be completed in accordance with the contents stipulated in the approved design documents. If the inspection and acceptance criteria are met, inspection and acceptance shall be organized in time for the transfer of fixed assets. However, before the completion acceptance, the construction unit should check whether it meets the requirements for completion acceptance. Only if the required conditions for completion acceptance can be met, relevant personnel can be organized to carry out the final acceptance. What are the specific conditions for completion acceptance ? Next, let's take a look with Xiaobian!
Completion acceptance conditions
1. Completed the project design and contract stipulations.
2. The construction unit inspected the quality of the completed construction project, confirmed that the project quality complied with relevant laws, regulations and mandatory standards for project construction, complied with the design documents and contract requirements, and submitted the project completion report. The report shall be reviewed and signed by the chief supervision engineer (project for commissioned supervision), project manager and relevant person in charge of the construction unit.
3, there is a complete technical file and construction management information.
4. All the departments responsible for ordering rectification by the competent administrative departments for construction and the entrusted project quality supervision agencies have completed the rectification.
5. For the engineering project entrusted with supervision, there is complete supervision data, and the supervision unit submits the project quality assessment report. The report shall be reviewed and signed by the supervisory engineer and the person in charge of the supervision unit. For projects not entrusted with supervision, the project quality assessment report is completed by the construction unit.
6. The surveying and designing unit shall inspect the design modification documents signed by the design agency during the survey, design documents and construction process, and submit a quality inspection report. The report should be reviewed and signed by the person responsible for survey and design of the project and the relevant person in charge of the respective unit.
7. Acceptance approval documents issued by the departments of planning, fire protection and environmental protection.
8. The project quality warranty signed by the construction unit and the construction unit.
What are the contents of final acceptance?
1. Check whether the project is completed according to the approved design documents, and whether the supporting and auxiliary projects are completed in synchronization with the main project;
2. Check whether the quality of the project meets the relevant design specifications and construction quality acceptance standards promulgated by the State and the Ministry of Railways;
3. Check the installation of engineering equipment and the installation and commissioning of equipment, and complete the contract for the introduction of foreign equipment;
4. Check the implementation of the budget estimates and the preparation of financial final accounts;
5, check joint debugging joint test, dynamic testing, running test situation;
6. Check whether the facilities for environmental protection, water and soil protection, labor, safety, health, fire prevention, disaster prevention and safety monitoring systems, safety protection, emergency evacuation passages, and office houses are completed and qualified according to the approved design documents. Whether the completed and retested results and related data are transferred to the equipment management unit, whether the work equipment and standing materials are in place according to the design, whether the geological disasters are rectified, and whether the seismic fortification of buildings complies with the regulations;
7. Check the completion status of the project completion documents, and whether the completion documents are complete and accurate;
8. Check whether the ownership of construction land is legal, whether the area is accurate, whether the boundary is clear, and whether the formalities are complete.
The above is the relevant content of the conditions for completion and acceptance. I hope to help you. For more information on completion acceptance, please continue to pay attention to information on this site.
Water and electricity acceptance paint construction acceptance inspection
Bread basket,stainless wire basket,stainless wire bread basket,Metal Wire Bread Basket,steel bread basket,etc. we offered that you can trust. Welcome to do business with us.
Kichen Rack is made of high quality 304 stainless steel, This kind of material steel luxury, never rust, resist corruption, easily clean, safe, healthy and durable. Prevent rust or chemicals from contaminating food and damaging health
stainless wire basket,stainless wire bread basket,Metal Wire Bread Basket,steel bread basket,versatile basket
Shenzhen Lanejoy Technology Co.,LTD , https://www.bbq-grillgrate.com